What we built
Built in December 2024, this stall for GTIS and Globetech Industrial Solutions works on two levels. A raised steel deck on blue columns carries a meeting area upstairs, reached by a yellow staircase, while the ground floor is given over to the material handling equipment the company sells: electric pallet trucks, a scissor lift table, a steel pallet and a mesh cage.
Design and finishes
The deck is built in the same blue and yellow as the equipment on display. Blue steel columns hold up a galvanised deck, and yellow handrails run around the edge and down the staircase, so the structure itself reads as part of the product story. Upstairs, white chairs sit around glass tables for meetings above the floor. Under the deck, the back wall is a printed graphic of the shelving and racking systems the company supplies, from long span shelving to mobile shelving and pallet racking.
At the open end, a tall header carries the GTIS logo on a backlit panel framed in blue. Below it, the side wall is a printed graphic with the Globetech Industrial Solutions and MHE names. Literature racks with brochures stand at the edge of the stall, and the floor is grey carpet.
Built in our factory
Two-level stalls need more planning than a single-floor build, so this one was worked out in 3D first, then built and dry-assembled in our Bengaluru factory. The deck, stairs and railings were put together there, checked for level and rigidity, and broken down into parts for transport.
On the floor
Our own crew put the stall up and handed it over before the show opened, then dismantled it after. The equipment sat on the ground floor where visitors could walk around it, with the team on hand beside the pallet trucks and the deck free for seated conversations.